Progress through July 3, 2008

The new C.E. Cole Intermediate School is currently under construction.  The projected final project completion is anticipated as August 8, 2008.

  • Site lighting continues
  • Curb and sidewalk started
  • Topsoil spreading started
  • Interior mechanical rough-ins continue in the cafeteria and media wings
  • Structural steel and decking is complete
  • Metal roofing continues at the media center
  • Painting is complete in the classroom addition and administrative wing
  • Painting started in the cafeteria and media wings
  • Kitchen renovations started
  • Trim out and ceiling tile started in the clasrooms
  • Window installation is complete, aluminum entrances started

GENERAL TRADES — E.R. Stuebner, Inc. – Contract #1

  • Kitchen equipment demolition
  • Set refrigerator and freezer boxes
  • Complete masonry
  • Complete structural steel
  • Start sidewalk and topsoil
  • Start bus loop extension
  • Started metal roofing
  • Continue doors and hardware at classrooms and administrative wing
  • Start aluminum entrances
  • Started drywall finish cafeteria and media wings
  • Continue terrazzo and epoxy flooring in cafeteria and media wings
  • Continue marker boards and tack boards in classrooms
  • Started toilet accessories
  • Started casework in classrooms and administrative wing
  • Completed elevator

ACOUSTICAL TILE CEILINGS — Supreme Ceilings, Inc. – Contract #2

  • Completed acoustical grid ceilings in administrative wing
  • Start grid in cafeteria and gym
  • Start laying tile in classrooms

CARPET/RESILIENT FLOORING — CB Flooring, LLC – Contract #3

  • Mobilize July 7, 2008

PAINTING — Hazelton Painting, Inc. – Contract #4

  • Complete finish walls classroom addition
  • Complete finish walls administrative wing
  • Complete finish locker room walls
  • Block fill and finish coat walls cafeteria wing
  • Block fill walls media wing

PLUMBING — G. Bass Company – Contract #5

  • Equipment rough-ins boiler room
  • Pipe insulation classroom addition
  • Complete rough-in bathrooms administrative and cafeteria wings
  • Start rough-in media wing
  • Set fixtures classroom addition

FIRE PROTECTION — Wayman Fire Protection – Contract #6

  • Complete sprinkler mains and branch lines second floor classrooms
  • Complete mains and branch lines in gym
  • Complete branch lines in boiler room
  • Start mains and branch lines cafeteria and media wings

HVAC — MBR Construction Services – Contract #7

  • Complete ductwork first and second floor classrooms
  • Set grilles, registers and diffusers classrooms
  • Rough-in pumps and boilers
  • Tie-in roof top units
  • Complete fan unit tie-ins classrooms, locker room and administrative wing
  • Set chiller
  • Set remaining roof top units for cafeteria and media wings

ELECTRICAL — Shannon A. Smith – Contract #8

  • Terminate panels
  • Install boxes and conduit in masonry walls
  • Devices in classrooms and gym
  • Fire alarm devices in classrooms
  • Technology wiring and devices in classrooms
  • Pull wire administrative wing
  • Set lighting fixtures in classroom addition

HAZARDOUS MATERIAL ABATEMENT — Altchem Environmental – Contract #9

  • Complete