Progress through July 3, 2008
The new C.E. Cole Intermediate School is currently under construction. The projected final project completion is anticipated as August 8, 2008.
- Site lighting continues
- Curb and sidewalk started
- Topsoil spreading started
- Interior mechanical rough-ins continue in the cafeteria and media wings
- Structural steel and decking is complete
- Metal roofing continues at the media center
- Painting is complete in the classroom addition and administrative wing
- Painting started in the cafeteria and media wings
- Kitchen renovations started
- Trim out and ceiling tile started in the clasrooms
- Window installation is complete, aluminum entrances started
GENERAL TRADES — E.R. Stuebner, Inc. – Contract #1
- Kitchen equipment demolition
- Set refrigerator and freezer boxes
- Complete masonry
- Complete structural steel
- Start sidewalk and topsoil
- Start bus loop extension
- Started metal roofing
- Continue doors and hardware at classrooms and administrative wing
- Start aluminum entrances
- Started drywall finish cafeteria and media wings
- Continue terrazzo and epoxy flooring in cafeteria and media wings
- Continue marker boards and tack boards in classrooms
- Started toilet accessories
- Started casework in classrooms and administrative wing
- Completed elevator
ACOUSTICAL TILE CEILINGS — Supreme Ceilings, Inc. – Contract #2
- Completed acoustical grid ceilings in administrative wing
- Start grid in cafeteria and gym
- Start laying tile in classrooms
CARPET/RESILIENT FLOORING — CB Flooring, LLC – Contract #3
PAINTING — Hazelton Painting, Inc. – Contract #4
- Complete finish walls classroom addition
- Complete finish walls administrative wing
- Complete finish locker room walls
- Block fill and finish coat walls cafeteria wing
- Block fill walls media wing
PLUMBING — G. Bass Company – Contract #5
- Equipment rough-ins boiler room
- Pipe insulation classroom addition
- Complete rough-in bathrooms administrative and cafeteria wings
- Start rough-in media wing
- Set fixtures classroom addition
FIRE PROTECTION — Wayman Fire Protection – Contract #6
- Complete sprinkler mains and branch lines second floor classrooms
- Complete mains and branch lines in gym
- Complete branch lines in boiler room
- Start mains and branch lines cafeteria and media wings
HVAC — MBR Construction Services – Contract #7
- Complete ductwork first and second floor classrooms
- Set grilles, registers and diffusers classrooms
- Rough-in pumps and boilers
- Tie-in roof top units
- Complete fan unit tie-ins classrooms, locker room and administrative wing
- Set chiller
- Set remaining roof top units for cafeteria and media wings
ELECTRICAL — Shannon A. Smith – Contract #8
- Terminate panels
- Install boxes and conduit in masonry walls
- Devices in classrooms and gym
- Fire alarm devices in classrooms
- Technology wiring and devices in classrooms
- Pull wire administrative wing
- Set lighting fixtures in classroom addition
HAZARDOUS MATERIAL ABATEMENT — Altchem Environmental – Contract #9
|